Why my Percentage of completion is so low?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Percentage complete at summary levels only works correct for money. (Primavera enterprise) because money is the only part what can be added. so Check if every activity has a cost budget. it can be from units (units x rate) or else. Check also if youve a budget (cost) at completion and check the earned value (cost). also check your actual and remaining costs. If these values are correct on activity detail your % complete on summary level should be correct.
kind regards
Henk
Hi,
Please, investigate the parameters of the 58% and 53%, maybe 58% is based on resources as you said but the 53% is based on total duration or cost. We need to compare two things in the same case means apple to apple not orange to apple.
best regards
Hi,
Check Summary bar "opition" !
Whether it is Duration, Resource or Cost ?
Cheers
Hi Juan
Did you checked the resource curve projection? is it linear?