weighting factor
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Previous discussions:
Weighting Factor
Schedule Performance Factor
Progress Measurement Units
Bernard Ertl
InterPlan Systems - eTaskMaker Project Planning Software
Agree there is not a standard.
You can use costs, man-hours, as urgency.
Some are more objective parameters other need an experienced evaluation.
In any case in a schedule try to be consistent, if You start in a way, go on with that one. Or You will start to loose control (will be difficult to intrepretate for You and Your management) of the results.
There is no standard on this one. Some may by the value of works, some may by urgency.