Quality Indicator

F
Forum Guest 👤 Member for 17 years 4 months
D
David Waring 👤 Member for 23 years 5 months

The only time when I have seen something similar used was on site, where resourced programmes were being progressed, and the data exported and integrated with actual cost information in Excel.

Part of the validation routine involved reasons for cost and time changes from planned to actual results - this included quality performance (errors, etc.) as part of the report.

It could possibly be done by categorising resources spent into Useful, Rework, etc. - but that would mean updating the resource allocation when entering progress- never a good idea!

M
MK TSE 👤 Member for 24 years 3 months

It seems nobody to use a programme for qulaity checking. The reason may due to the additional amount of quality related activity. As AA’s stated, how to reflect the re-work hour? Either a group of repeated or a proportional to the actual duration of the original. This make the network complex.

In P3, either user CDF to hold the proportion or introduce re-work activities. For P3e/c v4.0, may be simple just add one more issue/checklist against activity to create the Index.

B
Bernard Ertl 👤 Member for 23 years 6 months
Budget planned costs across a specified time period; the project’s estimated costs
BCWS Budgeted Cost for Work Scheduled to be completed within a given time period; [Budget] X [percent of the duration to the current date]; planned costs (budget) up to the current date
ACWP Actual Cost of Work Performed during a given time period; money spent up to the current date
BCWP Budgeted Cost for Work Performed; Earned Value; the dollar amount of work that was actually accomplished; [Budget] X [percent complete]
Schedule Variance SV = BCWP - BCWS; the value of what you have accomplished to date, versus what you planned to have accomplished to date
Cost Variance CV = BCWP - ACWP; the value of what you have accomplished to date, versus what you have spent to date
Schedule Performance Index SPI = BCWP / BCWS
Cost Performance Index CPI = BCWP / ACWP



Earned Value and Performance Indicator Definitions



Bernard Ertl

InterPlan Systems Inc. - Project Management Software, Project Planning Software

D
Dinesh Kumar 👤 Member for 22 years 5 months





SPI is Schedule performance index

CPI is Cost performance index



Regards



Dinesh

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts