Cost Loading in P3

F
Forum Guest 👤 Member for 17 years 4 months
M
Morteza Jafari 👤 Member for 22 years 10 months

the first I suggest to login to this site and be a permanant member, it will help you very much,

in response your query, I can summeraize my comments as follows:

lumpsum contract usually have a price/cost breakdown and this breakdown come in table and define elements of cost of project including engineering, procurement, construction and so on, if bidding be a completted package, it will certinally be in package, based on this table you should develop detailed price and input in P3.

I hope the above is clear.