Percentage Progess checking

F
Forum Guest 👤 Member for 17 years 4 months
R
Ronald Winter 👤 Member for 23 years 5 months

If you are using P3, there is a simple way to note project percent complete (using remaining durations.) Just run a CPM report. At the bottom (around the fifth line from the bottom, I believe,) there will be a listing of Project Percent Complete. Good luck!

B
Bernard Ertl 👤 Member for 23 years 6 months

Progress can be either a measure of time or effort (manhours). Since time and effort are not linear across the span of a project, I prefer and recommend that you measure progress in terms of manhours.



You can only qualify the overall percent complete if you can qualify the degree of accuracy in the estimating. Even then, you are assuming that the remaining schedule will stay within the margin of error recorded up to that point in time. This may or may not be a safe assumption.



Bernard Ertl

InterPlan Systems Inc. - Project Management Software, Project Planning Software

B
Bernard Ertl 👤 Member for 23 years 6 months

I think by "system" he means the software (P3 in this case).



[quote]for a simple Schedule with no resource planning how would you calculate the overall progress or how does the system calculate the overall summarized progress.[/quote]



Without resource planning, you are limited to measuring time. This is not a useful measure IMHO.



However, for each task, you can calculate:



Hours Elapsed / Hours Scheduled * 100 = Percent Complete



When calculating percent complete as a measure of time, each task is weighted the same, so average the percents complete across all tasks to find the total.



Bernard Ertl

InterPlan Systems Inc. - Project Management Software, Project Planning Software

S
Sagar Agrawal 👤 Member for 22 years 11 months

Thank you all for the reply



Well what I want to calculate is the overall percentage progress of the total project which P3 gives us when we summarize the whole project



Cause for that we are relying on the system.



I agree there could be weightage factors like Cost,Qunatity

but say that for a simple Schedule with no resource planning how would you calaculate the overall progress or how does the system calculate the overall summarized progress.

F
Forum Guest 👤 Member for 17 years 4 months

Using duration as weighing factor, you can check by computing manually using the formula (Sum of OD - Sum of RD)/Sum of OD.



OD - Original Duration

RD - Remaining Duration



For resource units the formula is AQ/BQ



AQ - Actual Quantity

BQ - Budgeted Quantity



For cost, the formula is AC/BC



AC - Actual Cost

BC - Budgeted Cost



You can check all these data by printing reports.


Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts