Primavera 6.0 inporting activity codes

Member for

20 years 4 months

actually Nancy,



This thread got lost. We are busy brainstorming the accreditation issue, then, suddenly out of nowhere you post appear.



I wish this post will disappear from the main thread and re-routed to the proper thread.



Cheers,

Happy Planning and Scheduling

Member for

19 years 10 months

Hi Nancy



Sorry but I have no Idea how P6 works - I use PowerProject.



Dieter seems to knwow what he is talking about.



Best regards



Mike Testro

Member for

18 years 9 months

Nancy

Resource codes are included within a xer-file ("RCATTYPE"). Codes marked as "secure codes" are not exported.



Regards

Dieter

Member for

18 years 9 months

Nancy

If you’ll create the EPS codes before importing - exactly same spelling, case-sensitive! - the values automatically will be included.

For the resource codes I’ll have to check at work. Did you check, if they are included in the xer-file? Maybe a problem of access rights during export.



Regards

Dieter

Member for

19 years 10 months

Hi Nancy



This should be in the Primavera section - not accreditation.



Best regards



Mike Testro.