Is there any Relationship b/w Performance% complete value & Total float value.....???

Hi Seniors,

I want to know is there any relation b/w performance% complete value & total float value. In my case, my schedule % complete value is 15.5 & performance % complete value is 11.

against these percentages my plan showing the delay of -14 days. I want to know why is much difference btw my schedule & performance percentage where my delay is only for -14 days.



please help me out with finest one.



 

Z
zahid shaikh 👤 Member for 9 years 9 months

1) Schedule % complete is calculated in P6 wrt to Baseline Planned dates and Data Date.

Eg: Activity start and finish are 22-Dec-17 to 2-Jan18 i.e. duration is 12 days. When data date is 25-Dec-17, (22-Dec-17)-(25-Dec-17)=4days. Schedule % will be 4days/12 days = 27%. For data Date 29-Dec-17. Schedule % will be 64%.

 

2) For Performance %; It is calculated wrt to Duration % complete/Units % complete/Physical % complete, depending on how the progress is being recorded. I.e Performance % complete is = Duration % complete (assuming that the project is resource loaded)

A
abubakar munir 👤 Member for 11 years 2 months

Thanks for your response.

I did not get it what are you trying to ask me but according to my understanding, i am measuring the performance w.r.t time.

 

Waiting for your reply.

A
abubakar munir 👤 Member for 11 years 2 months

Thanks for your response.

I did not get it what are you trying to ask me but according to my understanding, i am measuring the performance w.r.t time.

 

Waiting for your reply.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts