Hi Mary
My response below :
Level 2 : This normally is a Project Integrated Schedule - which includes all work broken down into manageable packages, where responsibility, time, cost and resources are embedded in the detail and interfaces between the work packages and functions identified.(Typically 250-300 activities depending on project size of course!)
Best Regards
Andy
Mary,
checkout this file:
http://www.planningengineers.org/knowledge/techniques/peo_technique3.pdf
Regards,
Karim
http://www.hud.gov/offices/cpo/evms/clause.pdf
Check the bottom of page 4.
Regards,
Andrew