Level 2 Schedule

M
Mary Folsom 👤 Member for 22 years 11 months
A
Andrew Donlan 👤 Member for 23 years 1 month

Hi Mary



My response below :



Level 2 : This normally is a Project Integrated Schedule - which includes all work broken down into manageable packages, where responsibility, time, cost and resources are embedded in the detail and interfaces between the work packages and functions identified.(Typically 250-300 activities depending on project size of course!)



Best Regards

Andy