Hi everyone, just wondering is there any one who is not ticking these two options and if yes, can you tell my you won't tick the boxes for these two? What would be the difference?
This is where you have your resources, under detail, profile.
Hi everyone, just wondering is there any one who is not ticking these two options and if yes, can you tell my you won't tick the boxes for these two? What would be the difference?
This is where you have your resources, under detail, profile.
Abbas,
'Calculate cost from units' means that the price of a resource assignment is calculated from one of the five available prices in the resource dictionary, rather than entered manually for each resource assignment. I ALWAYS tick this box, since it can be overridden for a particular resource assignment if there is a fixed price you must record independent of the resource quantity.
'Auto Compute Actuals' is ONLY appropriate if you do not have a timesheet system to record the real quantity of Actual aka expended quantities for each resource assignment. This fixes for the entire project a CPI of 1.00.