I have below question and I appreciate if you give me any soultion,
I have 8 projects and more than 40 contractors and one layout for each, every week I create 40 layouts and 40 repetitive works, is there any way to create PDfs from layouts in one click?
I also tried reports but as I have more than one projects open it dosen't save my repoort, and I think it is a bug from Oracle.
I look forward for any suggestion and thanks from now.
Stay safe
Mohammad
in P6 go to tools then reports then batch reports and batch them