Primavera Import: exported 1 line for the format, but copy and paste of "format" to the dates below does not work.

Primavera Import: exported 1 line for the format, but copy and paste of "format" to the dates below does not work.  It will not produce the black triangle in the upper left like the real exported dates  which states "Text Date with digit year" and when I copy the date format it turns the dates into excel dates in number format.  2nd question, does putting a ' mark in front of the id - is that enough to make it importable.  I have imported on and off for years - I just forget the nuances.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you cant import start and finish dates those are claulated

you can import constraint dates 

you  can import actual dates

1st export 1 activity of what you want thne use that as a template to import it back into p6

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you cant import start and finish dates those are claulated

you can import constraint dates 

you  can import actual dates

1st export 1 activity of what you want thne use that as a template to import it back into p6

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts