Would everyone here use a 3/1 data date for February progress?

Would everyone here use a 3/1 data date for February progress? (aside from some stated date like the 15th etc.) - this way it would match Feb. cost data etc., I always heard that the data date line was like 8am or whatever starting time.  I assume in theory that could be changed to 5pm or whatever ending time but I have never heard of anyone doing that.  

R
Rodel Marasigan 👤 Member for 19 years 7 months

The recommended and standard practice of data date is last working date and time of the reporting cycle.

Ex: Weekly cut-off = every Friday Cut-off at last working time say 5:00PM 

     Bi-weekly cut-off = alternate Friday Cut-off at last working time say 5:00PM

     Monthly cut-off = Last Friday of the Month at last working time say 5:00PM

     Shutdown per shift = Say at every 6:00PM 1st Shift and 6:00AM 2nd Shift

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts