when I import updated data I lose the WBS data, perhaps there should be no format when importing? Does certain wbs info have to be in the export - what am I doing wrong. Anytime I go a year without doing something I forget the associated "tricks".
when I import updated data I lose the WBS data, perhaps there should be no format when importing?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hey John,
Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
Hey John,
Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
Hey John,
Check your import settings, the last group is Project Data and there is a switch for WBS, maybe that has been changed?
John,
WBS has to be imported, or else all activities are by default dropped into the very top level node.