Hi Everyone,
I am having problems importing two MSP files that are saved as xml format. I have tried on our corporate SQLServer V20 and also on my Standalone SQLite V21.
The V20 import log just says Import: Failed
The V21 import gives me a message as Import Successful but the schedule does not appear in my projects list and the log file says, yep, you guessed it, Import: Failed.
Both times the xml file fails to import. Any ideas? I am happy to share the MSP files for you to play with.
Thanks, RJ
MSP to P6 never works well, its not the XML file format, its just the difference in the two applications. If its something you need to do often, I recommend looking into a Ms PRoject plugin called XER Transfer as the best option.
Hi Rodney,
Common error for importing MSP Project coverted to XML file is due to one of the following:
If you can share the MSP file to me, I can easily check the issue for you.