Issues when inserting P6 Programme

Hello house,

I will appreciate any help on the issue I am currently facing:

I copied a subcontractor Xer File to my Master Schedule . This plan was moved to a WBS within the master schedule, however I am now facing an issue where  a number of activities adopted a global calendar therefore their dates are all over the place

 

Is there a way I could this or I'll need to go back to the inserted programme and change the calendar manually ?

Secondly, when I aligned the calendar and schedule the programme, I notice the inserted programme now in a WBS of the master schedule is generating a negative float despite maintaning the same DD to the last secs.

Any guidance on the above 2 issues will be highly appreciated

 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

3 options

option #1

you can choose to not import calendars during the import process

Option #2

add column for calendars and do the 1st activity and the do a fill down

Option #3

run a global change to make all of the calendars the same 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

3 options

option #1

you can choose to not import calendars during the import process

Option #2

add column for calendars and do the 1st activity and the do a fill down

Option #3

run a global change to make all of the calendars the same 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts