Why can't I open two projects and copy activities from one to the other? the 2nd is just a later update, tries to paste back into the same project... - this should be easy, like from one spreadsheet to another - is there a trick to this? Pastes it back into the same one and want to just rename the activities....I guess I could export and import but surely there is an easier way....
Why can't I open two projects and copy activities from one to the other? pastes into the same...
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Wow, fastest answer ever on this site. Thank you very much.
Wow, fastest answer ever on this site. Thank you very much.
Yes there is a trick. Some of this might not be necessary now, but I always:
Group and sort by WBS
Do not 'hide if empty'
Always select using the left mouse button, before right-clicking and paste