Maintain Multiple Baseline with 1 step

R
Rami Louka 👤 Member for 6 years 6 months

Hi Guys,

I am dealing with window analysis with a lot if windows/projects/updates to compare, so here is my question:

How can I maintain multiple baselines to project in 1 step?? 

Again: I want to maintain two or three project to my current opened project in 1 step (1 click), is there a way sto select multiple projects and maintain them as baseline in 1 step?

 

Thanks for the help

Z
Zoltan Palffy 👤 Member for 16 years 11 months

its a 2 step process you can compare up to 3 baselines

1st select project maintain basleine then select assign baseline 

do this for up to 3 baselines 

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Rami,

That is not possible because the database only accept one at a time maintaining baseline and the same with assigning Baseline.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts