How to create Sr. No field in Reports using P6 Professional

I group the projects for a specific project code in Reports. But my Boss asks me to give serial numbers as i given below. I am unable to find any command to create this auto numbering serial for the grouped project code. Can anyone help me in this regard.

 

Open Projects      Sr. NoProject IDProject NameBudgeted Amount1Aasdf 2Bdfg 3Ccfds         



   

Muhammad Sajjad

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Mohammad,

You can copy and paste to excel the layout that you have in your Project Portfolio or Project Layout then you can do any counting or any formatting on your report. The best and quickest work around on your problem.

M
muhammad sajjad 👤 Member for 6 years 5 months

If i type in UDF, it will not show consecutive number after filtering or grouping a specific code. Can we count the specific code in P6 professional and put in reports? This may fulfill the need. For example if i froup the open projects i want to show the numbers against open open project heading like 10 or 20 what so ever.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Muhammad,

Primavera (P6) has no Auto Number Project Code in the system. The Line number function is only for Activity level.

My alternative solution is to create a Project Users Define Field  with integer settings and manually type the numbering system.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts