RESOURCES DISTRIBUTION WHEN UPDATING

Hi all,

I allocated revenues in a non labor resource assigned to activities. Now, we manually input the monthly revenues we forecast so that the curve for the remaining units (money) is not calculated by the software, maybe applying a resources curve, but it is set by ourselves according to our knowledge of what will happen.

So we have, for instance, 

    Data date    BudgetActualRemainingapr-21mag-21giu-21lug-21Activity1002080535,00,040,0

Now, when I update, even by giving to apr-21 the exact number as planned (i.e.),

the precise distribution of the remaining units is messed up and recalculated, and it becomes:

    Data date    BudgetActualRemainingapr-21mag-21giu-21lug-21Activity1002080525,324,525,3

How do I preserve, my original distibution?

thanks everyone that can help!

antonello

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts