Some Activity Name values are not seen when printing to PDF when using Enterprise version 18.8
Activity Name Fields Are Sometimes Missing In Printed PDF
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
haha yes. same issue.
have you re-booted the computer ?
"Yield=On" is already present in the PM.INI file.
But the error still persists.
The issue is caused by a missing setting in the PM.ini file.
SOLUTION
Edit the user's PM.ini file to add "Yield=ON" under [Printer Options] and save the file. After the user logs out and back in again, the change will be reflected.
The location of the PM.ini file may be in the default location (ex. C:\Program Files\Oracle\Primavera P6\P6 Professional\PM.ini) or in a user's "home" folder (ex. C:\Users\<User Name>\AppData\Local\Oracle\Primavera P6\P6 Professional\).