Hello Everyone,
Is there a way by which the Activity Bar which didnt meet the Basline Date can be highlighted in a different colour Say like Orange.
Red coloured bar is critical activity, but I would like to show activities which hasnt met the baseline date in Yellow.
Any chance ?
Thanks
Jithin
Hi Jithin,
you can create a new bar in wich you will assign a filter based on the "Variance BL1 Start Date", or "Variance BL1 Finish Date", or both
Alexandre