Export of Baseline

Hello Everyone,

 

I am using  P6.18.8.0 version.

When I export it in XER format, the baseline is not been exported.

when I export in XML format again the baseline is not exported.

Any solution to this.

Thanks

Jithin 

 

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Hi Alex,

 

Ya its working. I exported a XML File and the baseline was in it.

Thanks for the tip.

 

Regards

Jithin

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Jithin,

are you working stand-alone, or client-server? in this case, is it possible that you are not allowed to export baselines?

I am using P6 stand-alone with a SQLite database, and exporting/re-importing the baselines works perfectly with the XML format

Alexandre

S
Santosh Bhat 👤 Member for 21 years 2 months

Alexandre,

Yes you are corect. Sorry, its been a long time since I've had to use the XML format.

J
Jithin Kambhikanam 👤 Member for 15 years 2 months

Hi Alex,

 

I did export in XML Format, but again its not exporting the baseline.

 

And while exporting its asking if to include baseline and I have selected the baseline to be exported. But after exporting the and importing it to another machine I am not able to see the exported Baseline.

 

Is it a settings issue of Exporting Machine or Importing Machine ?

 

Thanks 

Jithin

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi,

Santosh, it is possible to export baselines together with the current project in the xml export process; you may select the baseline you want to export

I guess this option exists since P6 17.x at the latest.

Alexandre

S
Santosh Bhat 👤 Member for 21 years 2 months

Baselines are not exported to those formats, you need to go MAINTAIN BASELINES>RESTORE BASELINES then export this restored project seperately. Remembe to then re-attach the baseline to the original project.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts