Customising different column headers for different projects

T
Thomas Gude 👤 Member for 5 years 10 months

I am managing two different projects for different clients in P6 that require the schedules to be published every week.  The clients require different column headers and so far I have had to keep changing the headers when I go to publish each project.  Does anyone know of a way of saving the customised headers to be specific per project?

Thanks

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you can even export the layouts and send to someone else and they can import them and then they will not have to recreate them

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello Thomas,

Go to View, Columns; then, edit the column header and key in the header you want for this particular layout

Go to View, Layout, and save the current layout; then open another layout and you wil see that the headers have not changed

Customising a column header as well as Gantt chart bars, or any other item is only valid for the current layout, and has no impact on the other layouts.

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts