SS+Lag plus FF+Lag

I think we cannot have an activity with 2 relationships with the same successor activity(we need to decide the best logic) but my supervisor says we can have both SS+lag and FF+lag for one successor ! How can it be possible? it should be either SS+lag or FF+lag with the same successor. Do you agree or I'm wrong?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

this is known as a compound relationship and is common.

if you only use a SS this could happen

[[wysiwyg_imageupload:7515:]]

[[wysiwyg_imageupload::]]

R
Rafael Davila 👤 Member for 22 years 3 months

The risks of splitting activities that shall be executed continuously can be far more dangerous than pretending concurrent logic does not exists. This is specially true if your model is to apply resource constraints, it might spread apart the segments of an activity that shall be continuous. In such case use of SS(+lag) in combination to FF(+lag) relationships will make a better model.

Best Regards, Rafael

S
Santosh Bhat 👤 Member for 21 years 1 month

Sophia, this is a common technique to schedule activities that might happen in parallel, but where the second activitiy is delayed. 

Think for example if yoare digging a long trench, do you wait for the entire trench to be finished, before you start laying pipe? or can you start laying a pipe say once the trench has moved along by a distance? and in the same way, you cannot finish laying the pipe until some time after the trenching is completed.  so a SS/FF link to the same successory reflects this.

It might not pass the DCMA checklist, but in my opinion, that should not be a factor in determing whats realistic.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts