Shortcut key changes in R18

K
Kevin Smart 👤 Member for 9 years 7 months

We recently moved to P6 R18 from R8. In R8, the combination of Alt + V + F + Enter would open the filter list. It no longer does. Alt + V + F will show the filter option in the left side menu but hitting Enter no longer opens the filter list.

Does anyone know of a solution or has this very helpful feature simply been removed?

Much thanks for any help.