Late dates showing for some completed activities but not others? Why would this be? My assumption would be there is someting un-completed in the chain but that is not checking out. Not the biggest problem, but makes me think something is wrong.
Late dates showing for some completed activities but not others?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
John – “My assumption would be there is something un-completed in the chain but that is not checking out.”
Zoltan – “If an activity is complete there is no float. The only way that there would be a late date is if there is not an ACTUAL start or ACTUAL finish.”
https://www.linkedin.com/pulse/relationship-float-viewing-primavera-p6-santosh-bhat
Most software does not show early/late dates for completed activities. I cannot see a reason to show meaningless values.
if an activity is completed there is no longer a need for a late or early date. The difference between the early and late dates is the float. If an activity is complete there is no float. The only way that there would be a late date is if there is not an ACTUAL start or ACTUAL finish.