Imported XER showing as 4 separate items in the EPS

Afternoon all,

I've been sent an XER file of a single plan, yet once the import is complete it's showing as 4 separate items in the enterprise screen.  Open one and they all open, try to delete one and all go.  It's behaving as one but appearing as 4. 

Anyone got any ideas? Nearly 20 years of Primavera and I've not seen this before. 

Thanks, 

Thom

S
Steven Auld 👤 Member for 8 years 8 months

Thomas,

Sounds like the WBS on the import file is corrupt & instead of being seen as a child of the Project they are not getting the reference to the correct project ID & then showing as additional projects.

I have seen this a number of times, but usually when manually editing the WBS to add additional values.

When you delete the project that they are supposed to be under then the additional records should also be deleted.

This can also be caused by having certain punctuation in the WBS codes that have been added ouside of Primavera.

If you are able to share the file then I could have a look to check for these errors if you want.

EDIT - Apologies - never noticed that you had fixed it.

Regards,

Steven

T
Thomas Nicholson 👤 Member for 19 years 8 months

Hi all,

We think the problem has happened due to a Microsoft project import and it not having a parent to the included WBS. Solved it by creating a new empty plan and copying these into it.

Thanks for the suggestions

Thom

S
Santosh Bhat 👤 Member for 21 years 1 month

If the single plan you are looking at contains relationships to other projects, then a record of those proejcts will also exist in the XER and may get created when you import that XER. It may also be due to corruption of the data for the project, creating orphaned records that are also transferred in the XER file.

M
Mohammed Ali 👤 Member for 8 years 2 months

I think this problem because of the project WBS.

You have 4 Project Node in the WBS table under the same Project ID.

You may also have no parent for these 4 WBS Elements.

Be sure you have only one Y under the project node in the WBS Table.

Be sure that all WBS elements have a parent except the project itself.

P
Patrick Mullen 👤 Member for 6 years

Hey Tom,

I wouldn't mind taking a look if you want to send it to me. The only thing that I can think of is that they exported all 4 files at once, and you have them all open at the same time upon import. But if you want to send me the file, I can take a look.

[email protected]

Pat

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts