WBS description into Activity Description- Global change

Hi,

I am generating a engineering schedule. Our Client has asked to present schedule that it lists the control gates under each WBS.

I have listed the Deliverables at WBS level and would like to have the WBS name concatnated with the Activity Description.

For EX. P&IDs -- WBS Level

            P&IDs - IFR - Activity Level

            P&IDs - Receive Comments - Activity Level  so on for other control gate

the reason behind is without the description makes it difficult for sequencing.

Can some one guide me how this can acheived if possible.

Thanks in Advance,

Rajkamal

 

R
Rajkamal Tangirala 👤 Member for 16 years 2 months

Select Global change under Tools

 1. Create a New Global change

 2. Open the New Global Change

 3. Under the Select Subject Area to the left select "Äctivities

4. Under the first Option box set Paramater to "Any of the Following"

5. "Where" set Paramater to " Activity Name" " Starts with" " IFA/IFR/IFI"- the operator "OR" should be used for different Lines this shall be as per the line in the p6

6. Then in the output condition box the parameters as " Activity Name"  "=" Paramter Value "WBS Name"" operater "&" Äcivity Name".

[[wysiwyg_imageupload:7436:]]

 

R
Rajkamal Tangirala 👤 Member for 16 years 2 months

sure Sir Mr Zoltan

thist is what i had in my schedule

Then navigate to menu -> Tools-> Global Change-> modified as -> below

commit changes below is outcome

i require a hyphen that i inserted using the find and replace.

Thanks.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts