Hi, am trying to print out a project in P6, when i do a print preview, it shows another projects name from the Enterprize , when i go through the project information it has the right name on. How to i change this, i need to present the project to stakeholders
Wrong project name in Print preview
Forum Sponsor
Top Posters
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
It'll be in the page setup for that particular layout you are using (note each layout will have different print setup). select FILE>PAGE SETUP, then HEADER/FOOTER where the project name is. Find the section that is displaying the incorrect name, and then click on "MODIFY", you can either delete the project name and type in the correct name, or enter "[project_name]" to automatically get the name from the proejct information.