Dear All,
I am new user of p6 and actually i forget to make copy of base line program and updated progress . by checking start giving progress % and finish all activities which are complete. Now i need base line program back without progress.
Need Help
here is how to destatus a schedule
1. copy the current schedule
2. Choose Enterprise, Projects and select the Calculations tab. Choose to "Link Budget and At Completion for not started activities" and "Reset Remaining Duration and Units to Original
3. Choose View, Columns and add the columns for Actual Labor Units, Actual Nonlabor Units.
4. Choose Tools, Schedule and set the data date equal to the Project Start Date and schedule. To find the Project Start date, choose Enterprise, Projects. Click on the Dates tab and note the Planned Start date.
5. For the first activity in the list, set the Actual Labor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
6. For the first activity in the list, set the Actual Nonlabor Units to 0. Highlight the activities in this column and choose Edit, Fill Down.
7. Choose Tools, Global Change and run the 1st Global Change. This will set the Actual Material Units to zero.
8. Run the 2nd global change which sets the activity status to Not Started
1st Global Change
Subject Area:
Activity Resource Assignments
Where Resource Type equals Material
Then Actual Material Units = 0
2nd Global Change
Subject Area:
Activities
Where Activity Status is not equal to Not Started
Then Activity Status = Not Started
If this process is not used you may encounter the following error:
"Cannot set status to Not Started if activity has actuals."
3rd Global Change
Change duration to activities by running global change for Not Started activities
Subject Area:
Activities
Where Activity Status is not equal to Not Started
Then Remaining Duration = Original Duration
If you are recreating a schedule from an as-built schedule 1st export the actual durations to excel then import the actual durations as original durations.