Hi,
I want identify all the new activities i added to my original programme.
In order to do that, i think i need to create a filter that shows all the activities with no baseline but i cannot find a solution.
How do i create a filter that show all the activities with no baseline?
Thanks
Mike
Thank you so much!
Mike
Also of interest is when I need to identify and show all activities in compared schedule but absent in current version.
Use a filter with condition "Where BL Project Start (or BL Project Finish) Equals" and leave the value field blank.