Why ,at completion cost is different from budgeted total cost .
The cost is increased at completion cost from budgeted cost
Cost
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
put in the actual then adjust the at completion make it equal the budgted costs
i Checked it is Clicked even then, At completion Cost Is more than Budgeted Cost
go to Projects click on the calculations tab on the rigth under resource assignments
make sure that under
When updating actual Units or Costs that
Subtract Actual from At Completion is checked