Hello All,
I suspect the resource is not showing on the activities that are completed because it is a bit light after the progress line.
Please see image below.
The design activities are blue resources but i cannot see anything blue on the histograme blow after that progress / data date line.
I am suspecting the setting does not show the resources for activities that are completed but then, i can see slightly red for the construction activities which are in Red.
I am a bit confused.
Thank you for much for your help.
Kind regards
Mike Planner
[[wysiwyg_imageupload:7140:]]
go to view resource usage profile and make sure that on the dat tab that you have the actua box checked.
The P6 stacked histogram shows "At Completion" hours/costs - so stage 1 of your investigation is to show that value besiide the "Budgeted" numbers you have highlighted.......
Yes, "At Completion" is a bit bonkers....