P6 - resource is not showing activities that are completed

Hello All, 

 

I suspect the resource is not showing on the activities that are completed because it is a bit light after the progress line. 

Please see image below. 

The design activities are blue resources but i cannot see anything blue on the histograme blow after that progress / data date line. 

I am suspecting the setting does not show the resources for activities that are completed but then, i can see slightly red for the construction activities which are in Red. 

I am a bit confused. 

 

Thank you for much for your help.

 

Kind regards

Mike Planner 

[[wysiwyg_imageupload:7140:]]

Z
Zoltan Palffy 👤 Member for 16 years 10 months

go to view resource usage profile and make sure that on the dat tab that you have the actua box checked. 

D
David Kelly 👤 Member for 21 years 7 months

The P6 stacked histogram shows "At Completion" hours/costs - so stage 1 of your investigation is to show that value besiide the "Budgeted" numbers you have highlighted.......

Yes, "At Completion" is a bit bonkers....

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts