Hi,
Is there any way to make progress lines track the grouping of collappsed activities. I have late start activities and it tracks the individual activities and milestones but if I collapse them in group lets say grouped in Level 1, the progress line doesnt track the delays.
no and why would you want to do that anyway ?
Progress line functions only in activity level. Primavera doesnot recognize the Summary bars as activity and doesnot do any plan/actual calculation.