Global Resource vs Project Resource

What is the best practice on resource assignment. Is it good to create resources for each project or use the global resource. What would be issue if we just use the global resource, please.

S
Santosh Bhat 👤 Member for 21 years 1 month

In P6 there is no such thing as Project Resources, all resources are listed in a single Global pool. Your bext option is to organise the Resources into a hierarchy that matches your EPS structure and in that respect you can create project specific reosurces by naming them.