Every so often, my User Defined Filters get populated with these filters:
Critical_10
Has Finish Constraint
Has Start Constraint
Level of Effort_1
Level of Effort_3
Level of Effort_6
Milestone
Negative Float
Non-critical
Normal
After deleting, they will show up every so often. Any ideas how to permanently stop them from showing up in my User Defined list?
Thanks for looking,
CAM
No, they are not.
They seem to simply show up whenever they feel like it.
are they part of a layout that you are using ? if so they will still be there