Actual Finish Dates On Team Member

S
Steve Shunk 👤 Member for 13 years 10 months

Without going into the background, when using Team Member, our Task Owners often need to update their tasks on a Wednesday and they need to mark a task as finished and give it an actual finish date of Thursday or Friday, one or two days in the future. However, the software will not let the Task Owner enter a date beyond the current date. The future dates are grayed out.

Is there a way to assign an actual finish date that is beyond the current date? I know it is bad scheduling practice to assign an actual finish date that is in the future, but we have an unusual situation needing a work around. Any thoughts or suggestions would be greatly appreciated.

O
Ollie Lecm 👤 Member for 6 years 10 months

Maybe you can put a constraint of "Finish on/Mandatory finish" on it

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts