Activity cost as a percentage of the Project Budget Cost

Hi guys, I would like to express an activity cost as a percentage of the project budget cost. For example 

Project A - Total Cost is $5000

Project A has numerous activities and I would like a Column that expresses the Cost of the Activities as a percentage of Project A total cost. 

For example if Activity 1 within Project A has a total budget cost of say 1000. I would like a column that shows Cost % Budge of Activity 1 as 20%. 

I tried using the column "Cost % of Budget" and it was only giving me Zero % ages for every activity.

I would appreciate any form of assistance with this request. 

K
Kannan CP 👤 Member for 17 years 11 months

Rodney,

to do this exercise, create a UDF as number. export P6 to excel and then populate the new UDF column with a formula (as number, not %). and import it back to P6, you can see the contribution of each activity against the overall budget.

I believe that for the UDF import/export process, P6 is not supporting it with % figure, but only as a number.

 

Kannan

Z
Zoltan Palffy 👤 Member for 16 years 10 months

add a udf and then run a global change to do the math to get the percentage.

D
David Kelly 👤 Member for 21 years 7 months

Rodney,

I think you will find that niether you or the actual PC is responsible for this charming oversight......

R
Rodney Atuhaire 👤 Member for 6 years 10 months

Hi David thanks for this update. Thats exactly what I was avoiding to do. Honestly I thought there was an automated way of doing this. This problem was whacked my head so good. I felt like throwing the pc over the balcony. 

D
David Kelly 👤 Member for 21 years 7 months

Rodney,

No automatic way of doing this.  You would need to manually edit a Global Change script with the total project cost, so that you can calculate each activities proportion of it.  Every time any budget cost changes, you would need to edoit the script and run it.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts