I have taken over a schedule that is not resource loaded. However, management would like to add resources even though job has already started. The job is a EPC project. The constuction side is resoure loaded but not the engineering side. What would be the best solution for this task? Would I need to make a copy of the baseline, export, make the changes to include resources then import back in?
Turning a non-resource level schedule into a resource loaded one (P6)
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
add a labor resource
export both to excel
copy the non labor data values to the labor resource
import the excel file
deleted the non labor resource
done