Turning a non-resource level schedule into a resource loaded one (P6)

I have taken over a schedule that is not resource loaded. However, management would like to add resources even though job has already started. The job is a EPC project. The constuction side is resoure loaded but not the engineering side. What would be the best solution for this task? Would I need to make a copy of the baseline, export, make the changes to include resources then import back in? 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

add a labor resource 

export both to excel 

copy the non labor data values to the labor resource

import the excel file

deleted the non labor resource 

done