I need help in copying the activities and their durations (including WBS names) from primavera p6 to MSP
I have tried exporting the P6 schedule into excel and then loaded it into MSP, but unfortunately none of the activities were grouped under the respective WBS (so I spent the day creating summary tasks in MSP and copy pasting the activties in each WBS). The problem is that the P6 schedule has over 3000 activities.
I have also tried simply copy pasting the activties from p6 into msp but that results in errors and when I ignore them, the entire shcedule is pasted as activities (no WBS/ summary tasks)
Is there a faster (smarter) way of doing this? perhaps im pasting it incorrectly?
please help!
You may paste into Microsoft Project the Outline Level as a number to set the Outline of activities as you paste them in.
Paul E Harris
Eastwood Harris Pty Ltd
www.eh.com.au
Project Control Consultants and Planning and scheduling software book and training manual publishers
you can not do that
the resource that was added and assigned at the time time they were input remain in effect
solution create another resource
copy both to excel and populate the new resocue with the values on the old resource
import the resources then delete the resource no longer needed.
Hello dear,
i need help regarding primavera p6, i have assign the resources and i dont change the type of resource now i m trying to change the resouces type from labour to nonlabour, but they did not change.whats the easy way to change the resource type. please
Regards
Irfan Ali
[email protected]
Hello dear,
i need help regarding primavera p6, i have assign the resources and i dont change the type of resource now i m trying to change the resouces type from labour to nonlabour, but they did not change.whats the easy way to change the resource type. please
Regards
Irfan Ali
[email protected]
extremely sorry for the mutliple posts.
Cant figure out how to delete the repeated posts