i would like to create a large group of projects in p6. Is there a functionality to create a large amount of simple project in p6? Something like the batch to create financial period?
They must be simple, without activities, because I will edit them one by one.
Thanks,
E.
I use different software but got interested in your question, maybe the following will make it.
Good luck
Hi,
thank you for your suggestion, but I need to create different projects (with no activities), with different values for fields as project udfs or project codes. I would like to create a unique file with all projects in order to import it only once. I know that is just a dream. =S I tried with parser, but it is difficult to modify.
Thanks.
There is no batch feature, but you can select multiple projects at a time and copy and paste them.
So 1 copy = 2 projects
then 4, then 8, then 16, 32, then 64 etc..