Dear all, I just wanted to check whether somebody has practical and real experience of managing large projects (hundreds of tasks) with P6 EPPM (web-based). It is clear, that desktop version allows managing big project, but web-based??? Having working with it for a while now (with small projects) I have my doubts whether it is really usable for big ones. It is so slow, often loses connections and requires periodic browser refresh, because it stops working properly, that I am not sure at all it is practically usable for big projects. What is your experience?
Managing big projects with P6 EPPM (web-based)
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
From my experience I at the moment would like to warn anybody from using web version of EPPM.
I can imagine, that Oracle had to effectively rewrite a huge chunk of historical code first in Java and now in Java-script to move desktop version to WEB.
Whilst I admire the efforts they have taken, at the moment it just does not work well. Not to mention the natural limitation of not being able to manage thouthand of activities in Web interface, even with small amount of activities the software has a lot of bugs, some of them are difficult to hunt down, because they do not manifest 100% of time.
I do not know, when web-based version will be comparable with the desktop one in functionality and stability, if ever.
If you think of it, for a monster like Google it took more than 10 years of intensive development to bring Google Sheets to be comparable in functionality with desktop Excel (plus all collaboration features, which are great), but Google Docs for instance still lags behind MS Word, so my guess it will take Oracle a lot of time, before desktop version can be practically used.
Chary,
I did smile at your concept of a large project having hundreds of tasks. I would say more than ten thousand is large. The web based EPPM interface is unused in my client base, as a browser is no place to pivot 10,000 rows. The windows client works perfectly well with the EPPM database. You will continue to need the web interface for administration purposes. The Windows client often needs Citrix installed in order to function with good performance.
To continue on this topic.
Santosh,
Stick to the P6 professional client. EPPM web-based is not designed for large scale schedules.