Remaining Units not calculating - why?

Hi,

I'm back using P6 after a few years off and have been tasked with creating a resource histogram that shows the remaining hours.

Each time I run the report it is showing me the remaining actual units and not the remaining to earn.

eg.

Budget = 240, % Comp = 95%, Actuals = 210, Earned = 228

When I run the report it should tell me I have 12 hrs left remaining, however it says I have 30 hrs left.

I have my activities set up as Task Dependant, Fixed Duration & Units & Physical % Complete.

Any ideas?

 

Many thanks,

Gavin

Z
Zoltan Palffy 👤 Member for 16 years 11 months

are you updating remaining duration ?

what calculation are you using for earned value  ?

this is under

Admin Preferences

then the Earned Value Tab.

Technique for  computing Estimate to Compete (ETC) 

and  at the bottom Earned value calculation should be Earned value with current dates

 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts