Hi,
I'm back using P6 after a few years off and have been tasked with creating a resource histogram that shows the remaining hours.
Each time I run the report it is showing me the remaining actual units and not the remaining to earn.
eg.
Budget = 240, % Comp = 95%, Actuals = 210, Earned = 228
When I run the report it should tell me I have 12 hrs left remaining, however it says I have 30 hrs left.
I have my activities set up as Task Dependant, Fixed Duration & Units & Physical % Complete.
Any ideas?
Many thanks,
Gavin
are you updating remaining duration ?
what calculation are you using for earned value ?
this is under
Admin Preferences
then the Earned Value Tab.
Technique for computing Estimate to Compete (ETC)
and at the bottom Earned value calculation should be Earned value with current dates