Hi all,
I am currently collecting vendor plans which are mostly in MSP. I have have saved them as a XML and imported them into P6. However, for some reason the WBS heirarchy is being reordered in P6 which is effecting the activities view.
For example in the WBS it is ordered as
WBS CodeWBS NameABC.2 ABC.2.2 ABC.2.1 ABC.4 ABC.4.2 ABC.4.1 ABC.3
Obvisouly I can manually do this but it is very time consuming as I'm currently collating 30-40 plans and some will have to be re-imported as I improve the vendor plans.
I have never run into this before and tried looking at the import template but I can't see anything that might cause this. Also, I have not used my current employers P6 to import XML's before (I have previously used my own), so I'm not sure if it is something they have done that is causing this.
I hope someone can help with this. Thanks in advance.
John
There is converter if you give me your email I can send you the converter
Unfortunatly I can't. I'm using MSP 2010 and Googling the file type it says it was discontinued in MSP 2000. I don't have the option to save as MPX
have you tired importing an MPX file from MSP ?