I would like to update not add to an MPX file that is already been imported into P6. The drop-down menu doesn't give me the opportunity to update the existing file. Is there a way to update the project without replacing it.
Updating a MPX file
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Thanks, I'll do option 2 as I can import the file and then export as a xer and then do the update on the original file
option #1
open the project in p6 then you can select ADD to existing
option #2
if you have p3 or sure track convert the file from msp to either p3 or suretrack
then you can import the p3 project and use the update existing project option