Updating project plans

R
Ron Beechey 👤 Member for 23 years 11 months

I am currently in the role of project controls.   I receive from our contractors a weekly update in the form of a file to upload into P6.   Once I have imported or uploaded the project plan I will ensure the milestones are connected and then produce a complete start to finish integrated plan.  Included is a commissioning schedule.  

My question may be simple but is there a way or does the P6 program merge the next week plan replacing only the updated items or does it replace completely deleting the interconnecting links I made to each plan.    All schedulers work on standalone machines and they submit a new file each week.

 

Any help is appreciated. 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

this is the easiest way to do this. I would suggest that you keep updating the same project id but BEFORE you update it copy it so you have a historical record for that update period and add the date into the project name.

for example if the project id is named CAR and is statused as of Feb 1 then prior to updating it copy CAR and name it to

CAR1-020119

Now you can add the next months (FEBRUARY) progress to CAR

Next Month copy CAR to CAR2-030119

This way all ofyour layouys wont go to wates and can be used over and over again

This tells you the update # and the date of the update. Its simple but effective

R
Ron Beechey 👤 Member for 23 years 11 months

Thanks for the info.   Big help I was thinking that this would work but wondered if there was easier methods.   I will be doing this weekly as the contractors submit their updates.  Again thanks for the help.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you choose what do to during the update while importing 

Open the project in P6 then select file import then select xer and then find the file to import 

during the import options under the Import Action you can choose to Create New Project, Add Into Existing Project, Replace Existing Project or Update Existing Project 

You can select Update Existing Project 

Then under Update Project Options select Modify 

You will now be at the Modify Import Configuration screen

then you can choose what and how you want to import the information

There are 3 different categories 

Data Type: Activity 

Data Type: Global

Data Type: Project 

In each of these categories under the Action column you can choose to Update Existing, Do Not Import, Insert New or Update Existing.

for Activities you can just select Update Existing and the activities will be updated this this will also update the Activity Relationships and the Activity Resource Assignments

Under the Gllobal category thsi deals with Resources and can choose if you want to import them or update then you have the same actions available here.

Under the Project category you can update or add Activity codes, Activity code values, calendars and wbs

There is a lot of flexibility of how and what you want to import

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts