Team, I have a usser that has been locked out of P6 17.8 it is a STANDALONE VERSION and there are issues trying to log back in has anyone had this issue or encountered this before and if so what is the fix to clear the session????
How do you Kill a P6 Session in a Standalone environment
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
what is the lgo backin ISSUE ? whats the error ?
A Little more detail:
(This obviosuly only works if you are using P6 Standalone on a PC) - network issues will require an IT Administrator to resolve.
1) Click on Windows START>and type SERVICES
2) In the list of running Services, find SQL Server (SQLEXPRESS), right click and restart this service.
Otherwise DoduyKhuong has a great list of possible problems:
https://doduykhuong.com/2017/07/01/primavera-p6-professional-unable-to-connect-to-the-database-error/
Turn off the Primavera SQL service in Windows Services