Is there a setting so the Remaining duration updates automatically for activities which are in progress.
I.e. for a 10 day duration with an actual duration of 5 days then the remaining would be calculated to 5 days?
I currently have a 64 day activity, when I schedule it a a few weeks later than the start the remaining duration is still 64 days. It is set to Physical % Complete, at 95% complete.
I've tried to change lots of different settings in the project window, user preferences, schedule options etc.
Any help would be appreciated.
what you can is to run a global change to make the duration % complete equal to the physcial % complete
go to tool global change
New
where Percent Complete Type equals Physical
then duration % complete = Physical % complete
now on the rigth select Change
then on the botton right select Commit Changes