Overall Project Duration Based on Individual Project Default Calendar

K
Kannan CP 👤 Member for 17 years 11 months

Hi All,

I have recently imported few p6 files . The issue is that for some project's overall duration is not changing based on the calendar setting, coming under the default  tab of the Project. But the overall duration is only changing based on the selection of calendar under Enterprises......Calendar.....any Default calendar.

For few other projects, overall duration is changing perfectly according to calendar setting under the Default tab. Overall duration will not be affected, even if I select any calendar under Enterprises......Calendar.....any Default calendar.

Why this descrepancy, and I need to change the overall duration as per the calendar setting under the default tab of the Project.

Am i missing any setting.

Best Regards

Kannan

Z
Zoltan Palffy 👤 Member for 16 years 10 months

during the importin process check insert new calendars 

also just add a column and make sure that activites are using the correct calendar

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts